Electrical measurement cost calculator

Use the calculator below to estimate the cost of an electrical installation inspection. Enter the number of points for each type and the calculator will compute the approximate net and gross price (23% VAT). Rates are indicative and may vary depending on on-site conditions. A multiple socket outlet (e.g. double or triple) is counted as a single measurement point.

  • A legal requirement every 5 years. Under Art. 62 of the Polish Construction Law, owners and managers of buildings are required to carry out a periodic inspection of the electrical and lightning protection installation at least once every 5 years. Failure to do so may result in legal liability, especially in the event of a fault or fire.
  • A thorough inspection takes many hours. Properly testing every socket, fitting and circuit requires several to over a dozen hours of work, depending on the size of the property. The price reflects the actual time involved and the use of specialist measuring equipment.
  • Not every year – once every 5 years. Unlike e.g. a gas boiler service (required annually), an electrical inspection is needed far less frequently. Spread over 5 years, the cost is relatively low compared to the safety it provides.
  • The result is an official document. On completion, a measurement report is issued – a required document for building acceptance, property sale, or filing an insurance claim.
01 Sockets
DescriptionQty (pcs)Net rateNet total
Single or multiple socket outletPE, IPZ, insulation resistance
11.00 PLN
0.00 PLN
02 Lighting
DescriptionQty (pcs)Net rateNet total
Fixture without dismountingdirect access to terminals, PE continuity, IPZ, insulation resistance check
13.00 PLN
0.00 PLN
Fixture with dismountingPE continuity, IPZ, insulation resistance check after dismounting
19.00 PLN
0.00 PLN
03 Power circuits
DescriptionQty (pcs)Net rateNet total
Power circuite.g. induction hob, PE continuity, IPZ, insulation resistance check
14.00 PLN
0.00 PLN
04 Outdoor points IP44/IP65
DescriptionQty (pcs)Net rateNet total
Outdoor socketIP rating, PE continuity, IPZ, insulation resistance check
16.00 PLN
0.00 PLN
Outdoor fixture without dismountingIP rating, PE continuity, IPZ, insulation resistance check
18.00 PLN
0.00 PLN
Outdoor fixture with dismountingIP rating, PE continuity, IPZ, insulation resistance check after dismounting
25.00 PLN
0.00 PLN
Outdoor power circuitIP rating, PE continuity, IPZ, insulation resistance check
18.00 PLN
0.00 PLN
05 Distribution board / RCD
DescriptionQty (pcs)Net rateNet total
Panel inspectionvisual inspection
45.00 PLN
0.00 PLN
RCD 2-poletripping time and current
18.00 PLN
0.00 PLN
RCD 4-poletripping time and current
22.00 PLN
0.00 PLN
06 Equipotential bonding · Earthing
DescriptionQty (pcs)Net rateNet total
Main equipotential bonding bar (MEB)visual inspection
25.00 PLN
0.00 PLN
Element bonded to MEBpipe, bath, radiator, cabin – PE continuity
5.00 PLN
0.00 PLN
Earth resistance measurementIPZ method, 2-clamp
50.00 PLN
0.00 PLN
Earth resistance measurementtechnical method
150.00 PLN
0.00 PLN
07 Travel · Report · Installation layout reconstruction
DescriptionNet rateAmount
0.00 PLN
0.00 PLN
0.00 PLN
08 Discount
− no discount
Estimate summary
Net total
0.00 PLN
VAT 23%
0.00 PLN
Gross total
0.00 PLN

All rates listed are indicative and do not constitute an offer within the meaning of Art. 66 of the Polish Civil Code.